Algunos contenidos están en inglés. El texto original del anuncio es la referencia.

Électricité & génie climatiquedentro de 16 díasProcédure adaptée

Réalisation d'une étude d'impact environnementale, centrale photovoltaïque au sol à Digoin

Buyer

SEM SELER

Location

Saône-et-Loire

Deadline

04 dic 2026

dentro de 16 días
Published

03 nov 2026

Open the notice & tender file ↗ Read the expert study (in French) Download the bid file (ZIP, in French)

Bid file for one lot: lot 1 lot 2

To win this one

  • The stakes: Enjeu observé : 639 681 € (médiane du métier, 169 marchés), 3 offres attendues (médiane du métier, 117 marchés) ; environ 213 227 € espérés, ordre de grandeur, pas un devis.
  • The clock: 16 days: start this week, site visit or questions to the buyer before the end of week one.

Each line comes from a published measure (the notice's grid, awards, the buyer's history). A missing line means the data is missing, not that it is favourable.

Who won similar contracts

  • COLAS FRANCE ETS CHATELLERAULT, INEO MPLR - Agences Energies Nouvelles won « Travaux de construction d’une centrale photovoltaïque au sol hybride avec batteries - NAINTRE » with Société d'Economie Mixte Locale Sorégies (86) (Vienne) : 480 000 €, 5 bids, 17/09/2026
  • MIANE ET VINATIER, SOCALIM won « Réalisation d'études et travaux d'électrification, d'éclairage public et de réseaux de télécommunications - Lo » with S.E.H.V (Haute-Vienne) : 29/10/2026

Across these 2 contracts: median amount €480,000 (1 published) ; median of 5 bids (1 published).

Published award notices, matched by object, trade and département. Click a name to open its record: where it wins, at what price, against how many.

The essentials, in thirty seconds

Read straight from the notice the buyer published. It is not the consultation rules, which may add requirements, but it is enough to decide without downloading the file.

  • Bids due on 4 décembre 2026, in 16 days.
  • The contract is split into 2 lots. You may bid on the one that fits you only.
  • Duration: 30 months.
  • Variants are allowed: you may propose your own solution alongside the requested one.

The notice does not state : the question deadline, the score breakdown (l'avis ne publie pas de critères d'attribution), the estimated value. These are in the consultation rules inside the tender file.

Ask the buyer a question

contact@seler.fr +33 618959838

Open the tender file

How many rivals you actually face

sur les marchés « Etude », la médiane est de 4 offres par lot. 34 % des lots en reçoivent trois ou moins, et seulement 18 % dépassent dix candidats.

4bids per lot, median
6%of lots get a single bidder
34%of lots get 3 bidders or fewer

89 % des offres viennent de PME.

Stakes: Enjeu observé : 639 681 € (médiane du métier, 169 marchés), 3 offres attendues (médiane du métier, 117 marchés) ; environ 213 227 € espérés, ordre de grandeur, pas un devis.

Measured on 67 awarded lots that publish their statistics. 56% of buyers do; the rest say nothing, either way.

Run your radar to see how well this contract fits you, and get the next ones automatically. Describir mi actividad →

Données publiques officielles réutilisées sous licence ouverte, avec mention de la source et de la date. Reference 26-106711.