DAF_2026_000_570_Ochey (54)_BA133_Création SAS et réfection de la salle décontamination
SID NE
Meurthe-et-Moselle
16 oct. 2026
18 sept. 2026
The essentials, in thirty seconds
Read straight from the notice the buyer published. It is not the consultation rules, which may add requirements, but it is enough to decide without downloading the file.
- Questions to the buyer until 6 octobre 2026, i.e. 11 days.
- Bids due on 16 octobre 2026, in 21 days.
- A single lot: the contract is taken whole or not at all.
- La technique pèse 50 % contre 50 % au prix. Un bon mémoire passe devant un concurrent moins cher.
- Duration: 6 months.
- Estimated value: 160 000 €.
- environmental criteria are scored. That is where a local firm earns points a large group does not.
sid-nord-est.ach.fct@def.gouv.fr +33 3 83 87 64 50
How this buyer will score
La technique pèse 50 % contre 50 % au prix. Un bon mémoire passe devant un concurrent moins cher.
- 50pts 50 points
- 40pts 40 points répartis comme suit• Sous-critère n°1 - Indication des procédés d’éxécution envisagés, des moyens techniques utilisés et de la prise en compte du site occupé (15 points) ; • Sous-critère n°2 - Fourniture des fiches techniques d
- 10pts 10 points répartis comme suitSous-critère n°1.1 - Mesures de réduction des nuisances liées au chantier sur 5 points Le chantier se déroulant en site occupé, l'entreprise indique les mesures prévues pour atténuer les nuisances liées aux
How many rivals you actually face
sur les marchés « Bâtiment », la médiane est de 4 offres par lot. 46 % des lots en reçoivent trois ou moins, et seulement 3 % dépassent dix candidats.
88 % des offres viennent de PME.
Measured on 218 awarded lots that publish their statistics. 53% of buyers do; the rest say nothing, either way.
Données publiques officielles réutilisées sous licence ouverte, avec mention de la source et de la date. Reference 26-89740.