SGAMI33-2026-36-TX Marché de travaux relatif à la réalisation de l’étanchéité du toit-terrasse du Blockhaus / salle de sport et système pour recevoir des dalles sur plots au SGAMI SO à BORDEAUX (33).
SGAMI SUD-OUEST
Gironde
30 Nov 2026
29 Oct 2026
Bid file for one lot: lot 1 lot 2 lot 3
To win this one
- The price: Observed prices in this département (12 awarded contracts in this trade): a quarter under €109,150, median €300,704, three quarters under €2,752,519; published amounts, often framework maxima.
- The stakes: Observed value: €524,048 (trade median, 306 contracts), 3 expected bids (trade median, 197 contracts); about €174,683 expected, an order of magnitude, not a quote.
- The clock: 12 days: start this week, site visit or questions to the buyer before the end of week one.
Each line comes from a published measure (the notice's grid, awards, the buyer's history). A missing line means the data is missing, not that it is favourable.
Who won similar contracts
- Groupement EIFFAGE GENIE CIVIL COTE D'AZUR/TERIDEAL SEETA won « TRAVAUX DE RENFORCEMENT DE STRUCTURE POUR LA REQUALIFICATION DU MARCHÉ FORVILLE AVEC CREATION D'UN JARDIN SUR » with Mairie de Cannes (Alpes-Maritimes) : €7,406,230, 6 bids, 13/10/2026
- SOCOTRAS won « Entretien des joints d'étanchéité et réparation des fissures sur les espaces publics de la Ville de Vernon. Su » with Ville de VERNON (Eure) : €500,000, sole bidder, 22/10/2026
- SEG FAYAT, SOPREMA ENTREPRISES won « Travaux de construction des bâtiments B19a (SIREAUCO Pessac) et B19b (INSPE) sur le campus Bordes de l’univers » with UNIVERSITE DE BORDEAUX (Gironde) : €4,450,000, 13/09/2026
- SARMATES, LA LOUISIANE SA won « Travaux d'étanchéité et de charpente-couverture pour le patrimoine bâti de la Commune du Kremlin-Bicêtre » with Mairie du Kremlin-Bicêtre (Val-de-Marne) : €250,000, 6 bids, 04/11/2026
- CRUARD Charpente et Construction Bois SAS, LES MENUISERIES BOURNEUF won « Travaux de construction des bâtiments B19a (SIREAUCO Pessac) et B19b (INSPE) sur le campus Bordes de l’univers » with UNIVERSITE DE BORDEAUX (Gironde) : €2,336,692, 13/09/2026
Across these 5 contracts: median amount €2,336,692 (5 published) ; median of 6 bids (3 published).
Published award notices, matched by object, trade and département. Click a name to open its record: where it wins, at what price, against how many.
The essentials, in thirty seconds
Read straight from the notice the buyer published. It is not the consultation rules, which may add requirements, but it is enough to decide without downloading the file.
- Bids due on 30 November 2026, in 12 days.
- The contract is split into 3 lots. You may bid on the one that fits you only.
- Duration: 17 months.
- Estimated value: 5 403 999 €.
- environmental criteria are scored. That is where a local firm earns points a large group does not.
The notice does not state : the question deadline, the score breakdown (l'avis ne publie pas de critères d'attribution). These are in the consultation rules inside the tender file.
amelie.masse@interieur.gouv.fr +33 556997749
How many rivals you actually face
across French public contracts, the median is 3 bids per lot; 55% of lots get three or fewer, and only 9% get more than ten.
67% of bids come from SMEs, and in 20% of lots no SME bid at all.
With this buyer: 3 contract(s) from this buyer are indexed on its latest contracts, all trades, with no published bid count. Most frequent holder: KAPEA (2 times). Awarded amounts: median €201,611 (3 contracts, from €154,740 to €390,000).
Stakes: Observed value: €524,048 (trade median, 306 contracts), 3 expected bids (trade median, 197 contracts); about €174,683 expected, an order of magnitude, not a quote.
Measured on 4333 awarded lots that publish their statistics. 56% of buyers do; the rest say nothing, either way.