Maîtrise d'oeuvre technique et paysagère en vue de l'aménagement des espaces d'animation et de loisirs de la plage du Passet - Berre-l'Étang
Sens Urbain
Bouches-du-Rhône
30 Nov 2026
06 Nov 2026
Tender file pre-read
Upload the tender file: Tendveo picks out the submission deadline, site visit, minimum turnover, qualifications, technical requirements and contract clauses, each with the sentence of the document it comes from. An automatic reading to check, not legal advice.
To win this one
- The price: Observed prices in this département (26 awarded contracts in this trade): a quarter under €205,393, median €469,138, three quarters under €1,111,632; published amounts, often framework maxima.
- The stakes: Observed value: €317,865 (trade median, 376 contracts), 5 expected bids (trade median, 259 contracts); about €63,573 expected, an order of magnitude, not a quote.
- The clock: 10 days: start this week, site visit or questions to the buyer before the end of week one.
Each line comes from a published measure (the notice's grid, awards, the buyer's history). A missing line means the data is missing, not that it is favourable.
Who won similar contracts
- Groupement PROJET BASE (mandataire)/EGIS/COLOCO/PRESENTS/AGENCE OCCITANIE/TRIBU LYON/PASSE MURAILLE/BRUIT DU FRIGO/QUART, Groupement HYL HANNETEL YVER (mandataire)/SUEZ CONSULTING/SAFEGE/L'ADEUS-SOUS-TRAITANTS 8'18/GNI+/LE CABANON VERTICAL won « Maitrise d'oeuvre des espaces publics pour les travaux d'infrastructure de VRD et traitement paysager des voir » with Société d'Aménagement de Montpellier Méditerranée Métropole (Hérault) : 3 bids, 11/10/2026
- ARTELIA SAS, ALP'ETUDES INGENIERIE ET PAYSAGE won « Groupement de commandes - Accord-cadre de maîtrise d'oeuvre d'aménagement d'espaces publics » with GRENOBLE ALPES METROPOLE (Isère) : €3,000,000, 11 bids, 25/09/2026
- Ex&terra won « Maîtrise d'oeuvre pour la valorisation et l'aménagement de l'espace boisé du collège de Juvignac » with Conseil départemental de l'Hérault (Hérault) : €17,500, 13 bids, 15/10/2026
- V2S ARCHITECTES won « Marché public de maîtrise d'oeuvre en vue de la reconstruction de la piscine d'Hasparren (64) » with SPL PBA - Mandataire CAPB (Pyrénées-Atlantiques) : 27/09/2026
- SOCIETE POUR LA REALISATION D'EQUIPEMENTS ET DE CONSTRUCTIONS won « Missions de Maîtrise d’oeuvre pour l'étude et la conduite de travaux d’aménagement d’espaces publics de voirie » with Mairie de Suresnes (Hauts-de-Seine) : €240,000, 11 bids, 19/11/2026
Across these 5 contracts: median amount €240,000 (3 published) ; median of 11 bids (4 published).
Published award notices, matched by object, trade and département. Click a name to open its record: where it wins, at what price, against how many.
The essentials, in thirty seconds
Read straight from the notice the buyer published. It is not the consultation rules, which may add requirements, but it is enough to decide without downloading the file.
- Bids due on 30 November 2026, in 10 days.
- Duration: 14 months.
- environmental criteria are scored. That is where a local firm earns points a large group does not.
The notice does not state : the question deadline, the score breakdown (critères renvoyés au cahier des charges ou au règlement de la consultation), the estimated value. These are in the consultation rules inside the tender file.
How many rivals you actually face
on "Maîtrise d'oeuvre" contracts, the median is 5 bids per lot; 38% of lots get three or fewer, and only 26% get more than ten.
77% of bids come from SMEs, and in 21% of lots no SME bid at all.
Stakes: Observed value: €317,865 (trade median, 376 contracts), 5 expected bids (trade median, 259 contracts); about €63,573 expected, an order of magnitude, not a quote.
Measured on 84 awarded lots that publish their statistics. 56% of buyers do; the rest say nothing, either way.
Données publiques officielles réutilisées sous licence ouverte, avec mention de la source et de la date. Reference 26-108100.