Maîtrise d’œuvre pour les travaux de création de trois nouveaux casiers et la couverture de deux casiers sur l’Installation de Stockage de Déchets Non Dangereux de Saint-Christophe-du-Ligneron
Trivalis (85)
Vendée
08 Dec 2026
12 Nov 2026
Tender file pre-read
Upload the tender file: Tendveo picks out the submission deadline, site visit, minimum turnover, qualifications, technical requirements and contract clauses, each with the sentence of the document it comes from. An automatic reading to check, not legal advice.
To win this one
- The price: Order of magnitude of the trade across France (376 awarded contracts in this trade): a quarter under €153,543, median €317,865, three quarters under €740,267; published amounts, often framework maxima.
- The stakes: Observed value: €317,865 (trade median, 376 contracts), 5 expected bids (trade median, 259 contracts); about €63,573 expected, an order of magnitude, not a quote.
- The clock: 18 days: start this week, site visit or questions to the buyer before the end of week one.
Each line comes from a published measure (the notice's grid, awards, the buyer's history). A missing line means the data is missing, not that it is favourable.
Who won similar contracts
- AD QUATIO, RICHTER ARCHITECTES ET ASSOCIES won « CONCOURS OUVERT : CREATION DE TROIS UNITES D'HOSPITALISATION TEMPS PLEIN (UHTP) » with Etablissement public de santé Barthélémy-Durand (Essonne) : 3 bids, 19/11/2026
- ATOME, GIE DARWIN CONCEPT won « Accord-cadre d'Etudes et de Maîtrise d'OEuvre pour travaux sur les installations électriques » with GRAND PORT MARITIME DE LA REUNION (La Réunion) : €356,975, 6 bids, 18/10/2026
- ARCHISEN won « Concours de maitrise d'oeuvre pour les travaux de restructuration du gymnase de Saint Céré (46) » with CC Causses et Vallée de la Dordogne (Lot) : 55 bids, 08/11/2026
- DDL Architectes won « Mission de maîtrise d'oeuvre pour l'aménagement du nouveau Pôle Solidarités et Famille » with Département de la Vendée (Vendée) : €958,000, 3 bids, 11/10/2026
- SMTPC won « Conception et réalisation des travaux de construction d'un nouveau Centre d'Incendie et de Secours à Chirongui » with SDIS (976) (Mayotte) : €8,953,476, sole bidder, 22/10/2026
Across these 5 contracts: median amount €958,000 (3 published) ; median of 3 bids (5 published).
Published award notices, matched by object, trade and département. Click a name to open its record: where it wins, at what price, against how many.
The essentials, in thirty seconds
Read straight from the notice the buyer published. It is not the consultation rules, which may add requirements, but it is enough to decide without downloading the file.
- Bids due on 8 December 2026, in 18 days.
- environmental criteria are scored. That is where a local firm earns points a large group does not.
The notice does not state : the question deadline, the score breakdown (critères renvoyés au règlement de la consultation (« Offre économiquement la plus avantageuse appréciée en fonction des critères de j »)), the contract duration, the estimated value. These are in the consultation rules inside the tender file.
contact@trivalis.fr +33 251451451
How many rivals you actually face
on "Maîtrise d'oeuvre" contracts, the median is 5 bids per lot; 38% of lots get three or fewer, and only 26% get more than ten.
77% of bids come from SMEs, and in 21% of lots no SME bid at all.
Stakes: Observed value: €317,865 (trade median, 376 contracts), 5 expected bids (trade median, 259 contracts); about €63,573 expected, an order of magnitude, not a quote.
Measured on 84 awarded lots that publish their statistics. 56% of buyers do; the rest say nothing, either way.
Données publiques officielles réutilisées sous licence ouverte, avec mention de la source et de la date. Reference 26-110253.