The essentials, in thirty seconds
Read straight from the notice the buyer published. It is not the consultation rules, which may add requirements, but it is enough to decide without downloading the file.
- You have 4 day(s) left to ask questions (until 29 September 2026). That is the real deadline: after it, the specifications are frozen.
- Bids due on 9 October 2026, in 14 days.
- The contract is split into 2 lots. You may bid on the one that fits you only.
- Duration: 4 months.
- Estimated value: 0 €.
- environmental criteria are scored. That is where a local firm earns points a large group does not.
The notice does not state : the score breakdown (l'avis ne publie pas de critères d'attribution). These are in the consultation rules inside the tender file.
romain.cesbron@adoma.cdc-habitat.fr 0140614547
How many rivals you actually face
on "Assurance" contracts, the median is 2 bids per lot; 80% of lots get three or fewer, and only 4% get more than ten.
36% of bids come from SMEs, and in 63% of lots no SME bid at all.
Measured on 46 awarded lots that publish their statistics. 53% of buyers do; the rest say nothing, either way.